Case Study 1
Kirkstall Viaduct, Leeds

The council called us to erect some scaffold to form a barrier along the unsafe wall of the bridge. Concentrating on public safety we were required to make the bridge safe for pedestrians.

The scaffold was to be cantilevered out to allow access to the other side of the wall in order to make repairs.

Cantilevered and counter weighted/counter balanced scaffold to give access for rebuilding damaged parapet wall. This can been seen in the photos to the right, click to enlarge.

 

Photos
Temporary Edge protection to ensure the bridge is safe for pedestrians Temporary Edge protection Viaduct with  scaffold nsd ballast weight for counterbalance Viaduct with  scaffold nsd ballast weight for counterbalance
Temporary protection Temporary protection Viaduct with  scaffold nsd ballast weight for counterbalance Counterbalance
Temporary Edge Protection Temporary Edge Protection Viaduct with  scaffold nsd ballast weight for counterbalance
Click on the photos to view larger images
Viaduct with  scaffold nsd ballast weight for counterbalance
Viaduct with  scaffold nsd ballast weight for counterbalance
Viaduct with  scaffold nsd ballast weight for counterbalance

Case Study Index>>Case Study 2>>Case Study 3>>